MRP theory

 0    7 kartičky    dklekowski
stáhnout mp3 Vytisknout hrát zkontrolovat se
 
otázka English odpověď English
bull-whip effect
začněte se učit
small order changes in downstream demand lead to large upstream variation -> high unwanted inventories
lumpy demand effect
začněte se učit
Rip systems not first for unexpected, high demands
unreliability effect
začněte se učit
FG product consists of 5 parts, each of availability of 95%, then FG availability 77%
BOM
začněte se učit
bills of material
special BOMs
začněte se učit
modular bills, planning bills, phantom bills (used for subassies that exist temporarily
MRP requirements
začněte se učit
computer system necessary, mainly discrete products, accurate bill-of-material, accurate inventory status, stable lead time, problem with frequent re-planning
Four periods in the Rolling MPS
začněte se učit
Frozen - until week 4, new orders cannot enter and we can't change them; Firm - orders confirmed by customers; Full - we can shift things; Open - we can still assemble orders, we don't have to plan yet